HS2 Notification: North Chilterns newsletter
02/11/2022
HS2 Notification: North Chilterns Area Newsletter October 2022
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-CR-41-13/10/2022 | 1MC12-EKF-IN-NTE-CS03- 000043
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A413, Great Missenden, Little Missenden, Wendover
- Contractor
- EKFB JV
- Estimated Start Date
- 01/10/2022
- Estimated End Date
- 01/04/2023
What we are doing
Over the next couple of months, you can expect to see the following works in the local area;
- Sheet piling for the Rocky Lane bridge
- A413 London Road utility diversion and preparatory works for the temporary road realignment;
- Continued construction of the Bacombe Lane and Ellesborough Road temporary realignments;
- Construction and operation of our plant and vehicle crossings – Nash Lee Road and Bacome Lane;
- The start of our abnormal load deliveries to Great Missenden for the construction of the structures;
- Drainage surveys as well as topographical surveys involving lane and road closures;
- Ground Investigations, surveys and utility trial hole works;
- Continuation of the piling works for the Wendover Dean and Small Dean Viaducts;
- Ecology investigations and vegetation clearance works;
- A413 lane and road closures for utility diversions and excavation works;
- Chiltern Rail line temporary closures and possessions;
- Completion and operation of our conveyor;
- Excavation, movement, and storage of earthworks including temporary stockpiles;
- Operation of our new Rocky Lane compound.
Download information relating to these works
Find out more about
We'd like your feedback
Please help us improve how we keep you informed about how we're delivering the railway by giving us feedback on your experience.
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk